Summer Street Paving Heats Up in Dunwoody!

The 2015 street paving and street resurfacing program is starting to get underway and the city is anticipating work beginning the week of June 15 and continuing for approximately 10 to 12 weeks.  The city intends to work on a total of 48 streets, which equates to more than eight (8) road miles of paving and resurfacing. The city anticipates paving work on Vermack Road and Vanderlyn Drive to begin next week. CLICK HERE for the complete list of streets being repaved and/or resurfaced.

Additional roads from the city’s supplemental list and from future years could be addressed based on available funds and construction schedules. In December 2013, a special pavement assessment and data collection vehicle equipped with lasers, computers and other equipment drove Dunwoody streets to collect pavement condition information.  The truck gathered important data and measurements of overall roughness, rutting, cracking and general street condition to update the citywide pavement assessment. For more information about the assessment and future paving plans visit www.dunwoodyga.gov/paving.

STREET

START POINT

END POINT

Vermack Road

Parliament Drive

Dunwoody Square

Independence Square to

Chamblee Dunwoody Road

Peeler Road

Vanderlyn Drive

Vermack Road

End

Hidden Branches Drive

Mount Vernon Road

Winding Branch Circle

Pine Bark Court

Hidden Branches

End

Hidden Branches Close

Hidden Branches Drive

End

Hunters Branch Drive

Hidden Branches Drive

375 feet west

Pine Branch Point

Pine Bark Circle

End

Winding Branch Court

Winding Branch Drive

End

Old Branch Court

Twin Branches Way

End

Wellshire Lane

Wellshire Place

End

Equestrian Court

Equestrian Way

End

The Woodsong

Woodsong Drive

End

Woodsong Trail

Dunwoody Club Drive

Dunwoody Club Drive

Woodsong Drive

Woodsong Trail

End

Holly Oak Place

Chamblee Dunwoody Road

End

Sirron Court

Holly Oak Place

End

Shadow Court

Start

End

Pine Acres Court

Chamblee Dunwoody Road

End

Corners Cove

Vermack Road

End

Brandywine Court

Vermack Road

End

Manget Way

Chamblee Dunwoody Road

End

Vermack Ridge

Vermack Road

End

Dunkerrin Lane

Tilly Mill Road

Dunover Circle

Ledgewood Drive

Riverglenn Circle

Dunover Circle

Pine Branches Close

Pine Bark Circle

End

Pine Bark Circle

Hidden Branches Drive

Hidden Branches Drive

Claridge Court

Sudbury Road

End

Woodsong Court

Woodsong Trail

End

Withmere Court

Withmere Way

End

Reston Court

Withmere Way

End  

Shadow Bend

Chamblee Dunwoody Road

Shadow Court

Corners Drive

Vermack Road

Mount Vernon Road

Corners Court

Corners Drive

End 

Kings Down Court

Kings Down Circle

End

Santa Fe Station

Mile Post Drive

End

Topeka Court

Atcheson Lane

End

Amberly Way

Sudbury Road

Amberly Court North

Amberly Court South

Amberly Way

End

Trailridge Place

Trailridge Drive

End

Trailridge Pass

Trailridge Place

Trailridge Lane

Trailridge Lane

Hidden Branches Drive

End

Wickliffe Court

Kings Point Drive

End

Haverstraw Drive

Huntington Circle

Brookhurst Drive

Dunhaven Court

Dunhaven Road

End

Dunhaven Road

Brookhurst Drive East

Kings Point Circle

The following roads will be crack sealed as needed:

STREET

START POINT

END POINT

Perimeter Center West

Ashford Dunwoody Road

Crown Pointe Parkway

Peeler Road

Tilly Mill Road

Winters Chapel Road