Construction on the Dunwoody Village Main Street project began in December 2013 and work crews have cleared vegetation and trees from the parkway median. The initial clearing process lasted approximately two weeks and primary construction activities on the parkway began January 6, 2014.
Weather permitting, construction crews will be working on the village parkway median removal over the next several weeks. Crews will soon complete installation of orange safety silt fencing along the parkway followed by utility work along the thoroughfare.
Businesses along the parkway will remain open throughout the construction timeline. Please remember to shop local and visit all of the great businesses along the parkway! Click here to learn more about the Village Main Street project.