Dunwoody Village Parkway Construction Update

Source:  Councilman Terry Nall’s Newsletter

Public Works has advised that weather permitting, the final paving is scheduled to begin in early October and will last about a week. At that point, the heavy construction will be completed. Signage and final striping will follow. Then, the vehicle travel lanes will be relocated to the middle section of the Parkway, where the vehicle travel areas will be easier to navigate than the temporary construction lanes we experience today.  This is also when the dedicated turn lanes at each end of the Parkway will be opened.  The timing of the tree planting is expected to occur in November. Georgia Power indicates the decorative streetlight installation will likely be in December.

Staff is not aware of any pending snags at this time as long as we have dry weather until the paving is complete.