Dunwoody Village Parkway (DVP) Update

from Councilman Nall

 Road crews should finish the sidewalk, curbing, driveway entrances, and paving on the “Goodyear” side of DVP over the next two weeks.  Crews will then shift their work to the “Ace Hardware” side, thus moving traffic to the “Goodyear” side.  Please be alert to this traffic shift.  As a reminder, the timing of traffic signals at either end of DVP have been converted to fixed-time cycles until the construction is completed.  Once the project is completed, the signals will be re-set to operate on traffic detector sensors. Project completion is anticipated for early September.